Permit timelines across Metro Vancouver, mapped.

How long development and building permits really take in Vancouver, Burnaby, Richmond, North Vancouver, New Westminster and Surrey — and what makes approvals faster.

Permits & ZoningJuly 20267 min read

Permits are the least visible phase of a project and the one that most often wrecks a schedule. Here's how long approvals genuinely take across Metro Vancouver — and the preparation that reliably shortens them.

Typical combined timelines, city by city

The chart shows combined development permit and building permit duration for a new single-family or multiplex project, from complete application to issued permit, under 2026 processing loads:

4 mo8 mo12 mo16 moVancouverVancouver: 8–14 mo8–14 moBurnabyBurnaby: 6–10 mo6–10 moRichmondRichmond: 6–9 mo6–9 moNorth VancouverNorth Vancouver: 5–9 mo5–9 moNew WestminsterNew Westminster: 5–8 mo5–8 moSurreySurrey: 4–8 mo4–8 mo
Combined DP + BP processing ranges for new residential projects. Renovation-only permits and laneway fast-track streams typically run shorter; rezonings run far longer.

Why the same house takes 6 months in one city and 14 in another

  • Application completeness. The single biggest variable is whether the first submission survives intake review. Rejected-and-resubmitted applications restart queues.
  • Zoning conformity. Projects that fit outright zoning move through standard streams; variances and relaxations add board or council cycles.
  • Referrals. Trees, creeks, heritage character and steep slopes each trigger specialist review layers.
  • Servicing. New water, sewer or Hydro connections are their own approvals, best filed in parallel — not after.

How we compress the calendar

Pre-application reviewBefore design

We meet planning staff with a concept before drawings are finished, so the design answers objections that would otherwise surface at month four.

Complete-first-time submissions

Surveys, arborist and geotech reports, energy compliance and drawings filed together — intake rejection is where most delay is born.

Parallel processing

Demolition, servicing and trades permits are filed alongside the building permit, not after it.

Response discipline48 hours

When the city asks a question, the clock is ours. We answer revision requests inside two working days.

6Municipalities we file in weekly
Cost of a rejected first submission, in time
48 hOur revision response target
$0Feasibility zoning check
Planning tip: budget the permit phase honestly at the start and it becomes a scheduling fact, not a disappointment. We give you the municipality-specific range at feasibility, in writing.
Want your lot's real permit picture?

We'll check zoning, likely streams and current processing times for your specific address — free.

Book a Free Consultation

✱ Representative planning figures for Metro Vancouver, mid-2026 — assembled from municipal permitting schedules, the BC Energy Step Code framework and Armacan project records. Every lot and scope is different: treat these as orientation, not a quote, and confirm against your property in a free consultation.